May 4th, 2017
The latest group meeting discussed preliminary dates for the software demo, the comments Chris had made on our draft, information regarding the presentation and questions for Findwise.
See it all: Meeting 12 whole group
onsdag 10 maj 2017
Meeting 11: Whole Group
April 25th, 2017
The eleventh meeting discussed the following topics.
- The previous meeting with Chris
- The project plan and new deadlines
- The documentation
- The next e-mail to Findwise
See more: Whole group 11
The eleventh meeting discussed the following topics.
- The previous meeting with Chris
- The project plan and new deadlines
- The documentation
- The next e-mail to Findwise
See more: Whole group 11
Meeting 10: Whole Group
April 18th, 2017
The group discussed: the current Sprint, the upcoming Sprint and that Niklas and David should demonstrate the website to supervisor Chris.
Full minutes: Meeting 10
The group discussed: the current Sprint, the upcoming Sprint and that Niklas and David should demonstrate the website to supervisor Chris.
Full minutes: Meeting 10
Meeting 9: Whole Group
April 7th, 2017
During the meeting the progress with the current Sprint was discussed. The grade of the SRS1 document was shared (for those who had not seen it on other channels). The group should remain focused on the product. A potential group contract was discussed and posted on the group's drive.
Thony and Sara's showed the results from the user tests.
Want to see more? See: Group meeting 9
During the meeting the progress with the current Sprint was discussed. The grade of the SRS1 document was shared (for those who had not seen it on other channels). The group should remain focused on the product. A potential group contract was discussed and posted on the group's drive.
Thony and Sara's showed the results from the user tests.
Want to see more? See: Group meeting 9
Meeting 11: Group Leaders
April 5th, 2017
During the eleventh group leader meeting the following topics were discussed.
- The progress of the programming team
- Previous meeting with Chris
- The focus and the workload
For more see: Group leaders 11
During the eleventh group leader meeting the following topics were discussed.
- The progress of the programming team
- Previous meeting with Chris
- The focus and the workload
For more see: Group leaders 11